BATCH DIGESTERS
Digester change-out completed in 5 days.

New 80 Ton Batch Digester

new80tondigestor.jpg (34238 bytes)

Digester Being Readied for Lift System  

LIFT-DIG.jpg (70284 bytes)

Lift System Installed and Digester in its Initial Position for Hoisting  

LIFT-DIG2.jpg (65554 bytes)

Tail End of Digester  
Crane is used to support tail end of digester.

TAILCRANE.jpg (36551 bytes)

Digester in Upright Position  
Digester being rolled to its final location.

batchdigesters_ROLLOUT2.jpg (66238 bytes)

Lift System Permits Installation in Extremely Tight Quarters
Picture shows charging floor above.  Clearance less than one foot.

batchdigesters_ROLLOUT3.jpg (54670 bytes)